Key facts: Whitehaven coal mine

West Cumbria Mining Ltd want to extract 2.78 million tonnes of coking coal annually, right up to 2049.

Cumbria County Council approved the application; but campaigning, including a 114,000+ signature Coal Action Network petition, led government to make the decision itself and call a public inquiry. Subsequently the government approved the mine in December 2022, but the decision is subject to legal challenges. Work has not started and financing is not in place.

Key facts & figures

Coal & refuse to be excavated: 67 million tonnes in total - almost 3 million tonnes per annum (at full production) - WCM Planning Statement, Sep 2021

Coal to be sold: 64 million tonnes of coal in total - 2.78 million tonnes of coal per annum (at full production) - WCM Planning Statement, Sep 2021

CO2: Approximately 200 million tonnes of CO2 in total - 8.8 million tonnes of CO2 per annum at full production (2022 BEIS Conversion Factors)

Methane: 340,000 tonnes of methane which is 34 million tonnes CO2 equivalent (not included in the figures above) - 15,000 tonnes of methane per annum at full production (mid-range estimate, measured over 20 years, Global Energy Monitor's Global Coal Mine Tracker)

Coal operator: West Cumbria Mining (Holdings) Limited, which is 82% owned by EMR Capital Investment Limited (No. 3B PTE Ltd) registered in Singapore.

Type: Coking (metallurgical) coal

Claimed destination: primarily burned in steelworks in the UK and Europe

Local Planning Authority: Cumbria County Council

Address: from the former Marchon site, Pow Beck Valley, to St. Bees Coast, Whitehaven, West Cumbria

Physical size: principal seams to be worked would be the Bannock Band and Main Band, which are at a depth of approximately 350 metres over 23ha

Time: applying for planning permission from 2022-2049

Published: 03/08/2022

Share now:

Subscribe
Notify of
guest

1 Comment
Oldest
Newest Most Voted
Inline Feedbacks
View all comments

Never miss an update! Sign up to our Newsletter

OTHER STORIES

New advice shows Government how coal prohibition can prevent all new coal prospecting

In November 2024, the UK Government announced its commitment to legislating a ban of new coal mining licences. This was a commitment that Coal Action Network had secured a manifesto commitment from the Government for, along with four other major parties…

Barristers tackle tip law and licensing

Coal Action Network has obtained new legal advice from expert Barristers Estelle Dehon (KC) and Rowan Clapp of Cornerstone Chambers, London. Examining relevant…

Consultants enabling massive restoration cut

We informed each contractor what this mining company was up to, and the long record of criminal fraud, physical violence, and belligerence of David Lewis, the company’s director. Of those contractors, the ones listed below refused to rule out continuing to aid Merthyr (South Wales) Ltd dodge…

Lifting the lid on damage done by David Stanley Lewis of Pontypool

In 2015, David Stanley Lewis took over operations at the sprawling Ffos-y-fran opencast coal mine from the previous operator, Miller Argent. The company became ‘Merthyr (South Wales)…

Cross-party support at Senedd drop-in session to act on coal legacy

On July 1st, 2025, CAN organised drop-in session at the Senedd, spotlighting the urgent need for action on Wales’ coal legacy issues. The event saw strong cross-party engagement, with Members of the Senedd (MSs)…

Countering fake news in the Senedd

We’re actively setting the record straight when fake news about coal is spread through public figures, social media, or the press. The rise of populist politics and politicians tend to drive statements that are don’t entirely match the evidence, but may win them some votes…

360 exploration of Ffos-y-fran opencast coal mine

Explore the landscape via the images below, drag around the viewpoints and go full-screen for the immersive experience. This is what the 58,000 residents of Merthyr Tydfil face every day…and with a new plan by mining company, Merthyr (South Wales) Ltd, to evade its responsibility to restore…

Tip closest to residents to remain untouched

This information seeks to clarify which tips are included in ERI Ltd’s proposal to mine and then flatten certain coal tips in Caerphilly. The tips selected appear to be on the basis of which would be most profitable to mine of the ‘waste coal’ they contain…

The Bill that risks reigniting coal mining in Wales

The Welsh Government’s Deputy First Minister, in his response to the CCEIC’s Stage 1 Report, admits the “Bill does not prevent the extraction or burning of coal” but adds “I cannot envisage a scenario in which the extraction and burning of coal will arise as a result of the Bill”…

CONNECT WITH US

Share now:

1
0
Would love your thoughts, please comment.x
()
x