Coal Roundup September 2020

Opencast coal extraction

On the 8th September 2020, the Secretary of State for Housing Communities and Local Government rejected Banks Group's application to mine coal at Highthorn close to Druridge Bay, Northumberland. This is the second time a Secretary of State has rejected this application, following Northumberland County Council's 2016 approval of the opencast mine application.

This is a huge victory for Save Druridge the local campaign group against the mine. Local resident, Local resident Lynne Tate said, “The thought of this area being once again torn up, for a destructive opencast site over a period of seven years was unimaginable.”

Banks Group also had an application to extend their existing opencast mine in the Pont Valley, which it calls, Bradley rejected in July by Durham County Council.

There is currently only one opencast coal mine operating in England, none in Scotland and three in Wales.

The existing mines, by company are:

  • Celtic Energy: 1) East Pit, Neath Port Talbot and 2) Nant Helen, Powys (closure December 2021)

  • Merthyr (South Wales): Ffos-y-fran, Merthyr Tydfil

  • Hartington, Derbyshire.[1]

Banks Group proposed site:

Dewley Hill, on the outskirts of Newcastle, the planning hearing has been delayed by Covid protections.

Underground Mining

There are currently no underground mines operating of significant size

Proposed Underground Mines

West Cumbria Mining have amended their application for the land aspect of a new underground coking coal near Whitehaven in May 2020. If constructed this would produce coking coal for export for 50 years. Cumbria County Council has said a hearing date for a decision will be no earlier than October 2020.

New Age Explorations (an Australian company) are applying for licences for an underground coking coal mine at Lochinvar, on the border between England and Scotland. If constructed the company hopes to be producing coal until 2044.

Power Station Closures

Drax power station has announced that it will stop burning coal by March 2021 after almost five decades as one of western Europe’s most polluting power plants. Sadly the last two units are being replaced with another polluting fossil fuel, gas. Much of the wood which it burns comes from the clear-felling of biodiverse forests in Europe and the Southern USA which are home to many rare and endangered species.

EDF are reviewing the future of its West Burton power station, after the governmental support through the capacity market payments stop in September 2021. West Burton burns coal from Banks Group’s opencast mines in the North East of England, as well as imported coal.

Kilroot coal and oil power station in Northern Ireland is going to be converted to gas. No timeline for the end of coal use has been announced.

At Ratcliffe on Soar power station the owner Uniper plans to turn the power station into an incinerator for household waste and produce heat and electricity. There is no planning permission for this yet. United Kingdom withouth incineration network (UKWIN) highlight the problems with incinerators including air pollution and climate change, with a campaign against an incinerator at Ratcliffe.

The alternative fuels proposed at Ratcliffe, Kilroot and Drax would result in slightly lower greenhouse gas emissions and not require coal mining. However, these changes are not solutions to the climate or air pollution crisis and they involve building new infrastructure reliant on combustion leaving us dependent on fossil fuels or high levels of domestic waste.

Coal phase-out In early February the Prime Minister said that the coal phase-out could be brought forward from the end of 2025 to October 2024. This is not soon enough for communities at the front-lines of fossil fuel extraction.

Reduced demand for electricity due to the covid pandemic means that no electricity has been generated from coal since the 10th April 2020. 55 days and counting at the point of writing (4th June 2020).

Stockpiles

Total UK coal stock levels increased in 2018 to 5.3 million tonnes, broadly similar to the previous year. [2]

There is already more coal above ground than the UK government predicts will be consumed if coal were phased-out in 2025. We don’t need to extract or import any more. This is especially so, if the phase-out date is brought forward.

Want to help in the fight against coal?

References

References

[1] The Coal Authority, Production and Manpower returns for three month period January to March 2020 and other sources.

[2] Department for Business, Industry and Industrial Strategy, Statistical Press Release. UK Energy Statistics, 2019 & Q4 2019 (26 March 2020) page 6

Queries and media contact: info @ coalaction . org .uk (without spaces)

Subscribe
Notify of
guest

0 Comments
Inline Feedbacks
View all comments

Never miss an update! Sign up to our Newsletter

OTHER STORIES

Write to your MP to stop the Whitehaven coal mine proposal

The decision to stop or allow the proposed 61.4 million tonne coal mine has been delayed. We are keen to apply as much pressure to stop the mine as possible. Please join us in writing to your MP now to ask that they do everything in their power to stop the mine.

Key facts: Whitehaven coal mine

Coal to be excavated: 61.4 million tonnes of coal in total and 2.93 million tonnes of coal per annum (at full capacity)

Coal to be sold: 55.6 million tonnes of coal in total and 2.78 million tonnes of coal per annum (at full capacity)…

Lochinvar proposal – a licence to harm

New Age Exploration Ltd propose to extract up to 33.7 million tonnes of coking coal for steelworks in the UK and beyond between 2025 and 2051 near Carlisle, in South West Scotland. This may worsen local air quality, reduce the value of nearby residential properties, make local roads more dangerous with HGV traffic, and will emit around 73 million…

Anti-coal workshop – Earth First! Summer gathering

We will be running a workshop at this year’s Earth First! Summer gathering, which runs Wednesday 31st till Monday 5th in the South West of England.

Energy capacity market consultation response

We are concerned that the 2024 coal phase-out date is being used by the UK Government to deflect criticism for its support of using coal up until that date, when what we need is the most rapid phase-out of coal that is possible as the UK careers further from its climate targets…

Whitehaven coal mine decision due – Russia’s invasion of Ukraine is no excuse to mine

Several years ago West Cumbria Mining Ltd, backed by an Australian company applied to extract coal from a new underground coking coal mine under the sea by Whitehaven, Cumbria. A decision is now due, but there are some using the appalling invasion of Ukraine by Russia to justify more mining in the UK.

Utilities struggle to insure new coal power, contracts reveal

Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Nec dui nunc mattis enim ut tellus elementum. Massa massa ultricies mi quis.

Aberpergwm and the Well-being of Future Generations (Wales) Act

There is a law in Wales that helps the country all work together to improve the environment, the economy, the society and the culture. For people, for the planet. For now, and for our future. It is called the Well-being of Future Generations Act. Is it compatible with a coal mine extension at Aberpergwm?

Coal Action Network protest outside of Lloyd’s of London AGM

Last Thursday, 18th May, Coal Action Network protested outside of Lloyd’s of London, for their role in insuring the expansion of the Trans Mountain Pipeline (TMX) and the East Africa Crude Oil Pipeline (EACOP).

CONNECT WITH US

0
Would love your thoughts, please comment.x
()
x